Year
|
Client
|
Description |
| 2009 - 2010 |
ZCCM-IH (Zambian Consolidated Copper Mining – Investment Holding) |
Preparation of an Environmental Project Brief (EPB) and Design of Remedial Measures for Historical Tailings Material on the Banks of the Luanshya River Loan/Grant #: CR3741 ZA/H026 ZA |
| 2009 - 2010 |
Committee of Water Ressources, Republic of Kazakhstan, financing by Worldbank Komitee für Wasserres-sourcen der Republik Kasachstan (Finanzie-rung durch die Weltbank) |
Detailed Design of Works on Containment of High Priority Sources of Groundwater Con-tamination, Loan Agreement 4848 KZ Sources are five waste heaps with ashes and production residues from metal smelters and power plants, one tailings pond with Uranium and Thorium residues and one tailings pond, containing PCB's |
| 2007 - 2010 |
ZCCM-IH (Zambian Consolidated Copper Mining – Investment Holding) – halbstaatliche Organisation zur Privatisierung des Sambischen Kupferbergbaus
Finanzierung durch die Weltbank und den Nordischen Umweltfond (NEF) |
Remediation of radioactive Uranium tailings in Kitwe (Copperbelt, Northern Zambia)
Part 1: Safety and Environmental Assessment and Design of Remediation Works for Uranium Tailings at the AMCO Site Part 2: Monitoring and Supervision of the Remediation Works for Uranium tailings at the AMCO Site, Kitwe/Zambia |
| 2007 |
UNDP United Nations Development Programme, Kosovo Mission (Pristina) |
Environmental Assessment and Remedial Action Plan (EARAP) at Stan Trg/Stari Trg and Artana/Novo Brdo Mines, Emergency measures were derived based on analysis of the real situation, which included mine water management, dust prevention, management undisturbed surface runoff, relocation and erosion protection of Pb/Zn tailings heaps. Complete bidding documents for the detailed design, works and supervision have been prepared. |
| 2006 - 2009 |
European Commission, EuropeAid (EU TACIS Program), Brussels |
Development of a prototype monitoring, information and early warning system for the Ob/Irtysh river basin, EuropeAid/121579/C/SV/RU |
| 2005 - 2011 |
Committee of Water Resources, Ministry of Agriculture of the Republic of Kazakhstan, using funds of the World Bank (Grant Agreement No. TF 051352), Ministerium für Kata-strophenschutz der Republik Kirgisistan (Finanzierung durch die Weltbank) |
Dizaster Hazard Mitigation Project (DHMP) - Remediation of the Mailu Suu Mining and Milling Wastes
Project management, design, EIA's, project supervision of remediation measures for dumps and tailings pond, residues of former Uranium mining and milling in Mailuu Suu. Construction of a new storage cell for radioactive material, relocation and remediation of radioactive tailings material |
| 2005 - 2006 |
MGG Montangrundstücksgesellschaft mbH, Quierschied-Göttelborn, Germany |
Design and project supervision on securing and remediation of the “Erna” mine shaft |
| 2004 - 2006 |
Deutsche Steinkohle GmbH (DSK), STEAG Saarenergie, Germany |
Underground water dam in the Warndt-Luisenthal coal mine, The geotechnical conditions of the surrounding rock were complicated. The hydraulic head above the dam was predicted to be 1100 m, which led to a challenging geotechnical task. Geo-hydraulic conditions in the rock were also not trivial, which necessitated extensive geo-hydraulic testing and a very close supervision of the dam construction works. |
| 2004 - 2005 |
Ministry of Regional Development, Republic of Bulgaria, using funds of the European Commission (EuropeAid/113349/D/SV/BG) |
Remediation Programme for the Uranium Mines in Southern Bulgaria |
| 2004 - 2005 |
MONTEC GmbH on behalf of the mining authority (Bergamt) of the federal state of North Rhine Westphalia, Germany |
Securing of the “Siegen-Rosterberg” damage, caused by historical mining activities, In January 2004 a sudden subsidence occurred, caused by historic mining activities of a former iron mine in the settlement “Rosterberg” of the town Siegen. Residential houses were seriously damaged, and quick action to prevent the residential area from further collapsing was required |